Frequently Asked Questions
How can we help you?
The Project
Where is the Project?
How big is the Project?
How tall will the turbines be?
Are transmission lines required for the wind farm?
Are new roads required for the wind farm?
St Patricks Plains wind farm will construct new unsealed access tracks linking existing Council roads to the turbine locations. In many cases, the new tracks will involve upgrading existing farm tracks, which will also help landowners with farm operations, and potentially emergency responders in the event of bush fires or other emergencies. In all cases, the new access tracks will be designed with the objective of minimising impacts to existing vegetation.
The new access tracks will be unsealed but will be constructed to allow for transport of heavy materials and equipment during construction, and to allow for long-term operation of the wind farm.
St Patricks Plains will be working with Council to assess the local road network and identify any road upgrades required to support project traffic requirements.
Project Impacts
Will there be an impact on flora and fauna?
The proposed development must satisfy the very stringent biodiversity impact assessment requirements of both the Tasmanian Government (via the Environmental Impact Statement – the EIS) and the Federal Government (through the Environmental Protection and Biodiversity Conservation Act).
Specialist consultants have undertaken detailed flora and fauna surveys of the site. Both desktop and field surveys have been conducted to establish the ecological attributes of the land.
St Patricks Plains wind farm is minimising the impact to local flora and fauna through designing the project to avoid areas of high conservation significance. During construction, we will adopt best practice control measures to minimise impacts to biodiversity.
Will turbines affect property values?
Several studies commissioned by the NSW and Victorian governments have examined potential impacts of wind farms on property values and have found no evidence that wind farms lower rural property values, including the Assessment of the Impact of Wind Farms on Surrounding Land Values in Australia (Preston Rowe Paterson, 2013) available here.
What is the economic impact of the project?
Socio-economic modelling of the Project was undertaken and the total expenditure for the development of the project was modelled at $980 million, with 14% or $80.5 million of that spent directly within Tasmania. The modelling suggests that as a result of the project, gross state product in Tasmania would increase by $64.4 million over the construction period, driven by expenditure in materials, professional services, the workforce and associated upstream and downstream industries such as accommodation, services and transport.
How will workers be accommodated for the project?
Do wind farms impact livestock or farming operations?
The majority of wind farms are developed on agricultural land and wind turbines are very much compatible with existing farming operations. Turbines occupy only a small amount of land, and landowners can continue normal grazing or cropping activities. Livestock has often been seen using turbine towers for shade and shelter from wind and rain. The income provided to landowners hosting wind farm infrastructure can help make farms more resilient to the impacts of droughts, fires and commodity price fluctuations.
Will there be an impact to cultural heritage?
At all times, the project will be developed in compliance with laws regarding the protection of cultural heritage.
Project Benefits
How will the community benefit from the Project?
- The Project will deliver significant benefits to the local region including:
- Significant investment in Tasmania
- Opportunities for local contractors and businesses
- Up to 200 new jobs expected to be created during construction
- Development of new skilled labour in the region within the growing renewable energy industry.
How many jobs will the Project create?
The Project will create up to 200 new jobs during construction. Construction and operation of the Project will require a range of skills including engineering, trades (electrical, mechanical, construction), transport, building material providers, equipment operators, consultants and administrative staff.
Will there be a Community Benefit Fund?
Project Construction
When will construction commence and how long will it take to build the wind farm?
We expect to begin construction in 2027. Construction will take around three years to complete.
Where will water be sourced from?
How will turbines be delivered to site?
It is expected that wind turbine components would be shipped to the Port of Bell Bay on the Tamar River in northern Tasmania and transported to the site in early morning convoys via the same route used for the Cattle Hill Wind Farm: Bell Bay Road, East Tamar Highway, Midland Highway and Highland Lakes Road via Bothwell.
The delivery of the larger turbine plant will be undertaken by Oversize and Overmass (OSOM) vehicles. The delivery of the turbine plant will be conducted by a specialist transport company with experience working on wind farm projects. Vehicles are subject to specific permits, ensuring the proposed delivery method is undertaken in a considered manner acceptable to the road authorities. These trips are extraordinarily well-planned and coordinated to ensure public safety and traffic control where required. Drivers are professional and highly experienced.
Delivery of equipment and machinery would generally be isolated trips from suppliers locally and further afield, at the start and end of the project.
Will the local roads be sufficient to transport the wind turbine blades and towers?
To minimise impacts on the local community, we will be using major roads to access the construction site whenever possible.
We will also work with road authorities and local councils to prepare a Traffic Management Plan before construction, describing how we will manage traffic and transport to ensure efficient and safe movements.
How will vehicles access the Project area?
Is there a Traffic Management Plan?
What are the hours of construction?
How can I register my interest in providing services to the wind farm?
Local suppliers, businesses and property owners are encouraged to register their interest in providing services or accommodation by sending their details via our info email with ‘Supplier enquiry’ as the subject. Construction is currently targeted to commence in Q2 2027.
We will hold contractor information nights in late 2026 as we get closer to the start of project construction.
Operations
Are there any health risks associated with the wind farm?
Will there be noise from turbines?
Will the wind turbines have lights?
Is there any fire risk?
The Project poses a low risk of fire ignition with appropriate mitigation measures in place and would not present significant limitations to fire services in the event of bushfire in the region.
Fire risks during the operational phases would be managed in line with relevant health and safety legislation. An Emergency Response Plan will be developed and incorporate a Fire Management Plan completed in consultation with the Tasmania Fire Service and local fire chiefs.
Where will water be sourced during Operations?
Is there any risk to the wedge-tailed eagle?
There will be a minimum 1 km buffer to known wedge-tailed eagle nest sites and installation of wind turbine curtailment technology to minimise collision risk.
Major design revisions have been made to avoid areas used by eagles and the Identiflight curtailment system will be installed to achieve full coverage across the site and minimise collision risk.
Decommissioning
How long will the wind farm operate?
What happens at the end of project operations?
What is the decommissioning process?
The decommissioning process would involve the removal of wind turbines, electrical infrastructure and buried cables, and the site would be returned to its former state where practicable.
The concrete foundations will be removed to a depth of at least 500mm, but the bulk of the foundation will be left in-situ. The excavated area will be backfilled with compatible local material and then covered with topsoil to ensure that grazing and farming activities can be resumed.
A Decommissioning and Rehabilitation Plan will be provided to the Director, EPA for approval within three years of completion of construction.
Wind turbines are predominantly made of recyclable materials and approximately 88% of the wind turbine is recyclable. Research and developments in technology continue to advance recyclability of wind turbine components with the aim to achieve 100% recyclability before the end of wind farm operations.